garden city bowl

client

QBE Insurance

timeframe

Assessment & planning: Nov 2011 - Feb 2013

Building work: Feb - Mar 2013

total value

$100,000

project description

The Garden City Bowl repair is typical of much of the work undertaken by Sidera since the Canterbury earthquakes. The business operates 12 hours a day, 7 days a week, and was shut for just one week while the franchise owner undertook a fit-out. The building repair work included crack injection to most wall panels, roofing repairs, weatherproofing and repainting, and was completed within the fit-out timeframe, accommodating tenant needs. A highly specific floor level survey was commissioned.

project detail

Follow the link for more project detail and images

our role

  • Project management of earthquake repair process
  • Insurance claim management

particular challenges

  • Business remained in operation 12 hours a day 7 days a week during repairs
  • Work was completed to meet a time frame set for tenant fit out
  • Proximity to KiwiRail line created health & safety issues
  • Worked with neighbouring business to access some repair areas

outcome

  • Met original insurance scope costings
  • Completed to suit tenant's timeframe
  • Able to work with tenant to put new branding in place
  • Non earthquake repair issues were identified, assisting owner with maintenance issues